Message from Wessex Water :
“I have received confirmation from Wiltshire Council that the resurfacing works have been amended, and access for the village should not be affected on Saturday.
Unfortunately, our pipe supplier has delayed the delivery once again; however, they have assured us that the pipe will now be delivered on Monday. As soon as the pipe arrives, we will begin laying it and reinstating the excavated area so that we can move on to the next stage of the works.
While this does result in a delay to our programme, we are confident at this stage that the time can be recovered during the next couple of sections.”