Update from Dan at Wessex Water
Progress This Week
• Approximately 200 metres of 180mm water main have been successfully installed.
• Trench concreting works have commenced in preparation for upcoming surfacing activities.
Planned Works for Next Week
• A planned shutdown at Folly Fields junction is scheduled for 19/05/2026.
• Following the shutdown, works will continue with:
o Backfilling of all trenches from Folly Fields through to the Charlton end of the road closure.
o Tarmac surfacing works, which are programmed for completion ahead of the bank holiday.
Traffic & Access Arrangements
• From 23/05/2026, all residents in the Folly Fields area will enter and exit via the Charlton end only.
Summary
• This week: 200m of 180mm main installed; trench concreting underway.
• Next week: Junction shutdown (19/05/2026), followed by backfilling and tarmacking works in preparation for the bank holiday period.
Michael has clarified that the access to Follyfield will be maintained using Road Plates in a similar way to this week.
We also had a letter (Follyfield) that said the water supply may be interrupted on Tuesday from 10am – 1pm.