The Wessex Water updates have moved from informative, to succinct, to minimal, and now to non existent for the last two weeks !
I’ll chase Dan, Dan, the Engineer Man next week.
As far as I can see though they’re pretty much on target :

I can see that the drilling exit hole has been filled in and the trench leading to Dove House is backfilled with concrete so just needs a tarmac topping to finish off. I’m assuming that will happen next week so they may actually be slightly ahead of schedule.