This weeks update from Wessex Water :
Continuing on from the previous work, another 100m section has been complete along with reinstatement, with the same to be completed next week.
In addition to this, we are aware of a leak which is currently occurring outside Dove House, so if any residents are concerned, please can you inform them that the work to fix the leak will be taking place on Monday 13th July at night.
I think they’re slightly ahead of schedule ?
I assume that fixing the leak will mean that the single lane they normally keep open will be closed on Monday night.