Unfortunately Dan hasn’t updated us again this week so this is just my opinion !
There’s a large hole at the turning to Eastcourt and it looks like they’re building a set of pipe junctions to connect to the existing pipework. No way through at the moment by road.
At the other end (junction with Cloatley Rd) there’s another hole with fittings as well. It looks to me as if they’re getting ready to connect the two ends up to replace the existing pipework.
After that I’d guess there will be testing and snagging… no idea how long that would take I’m afraid !
So my guess is that the last section including the final connections would take a little longer than the other sections so the plan would look like this :

But remember, this was always my guess at the plan not their plan !