Roadworks

The one.network website shows the project finishing on 28th August.

The Design Engineer said that the work will be in sections of roughly 100m-150m, so with the help of Google maps I’ve estimated the different sections of work and how long they’ll need to take to hit that date.

The last “section” is Wessex Water chlorinating the new pipe, testing, and finishing off.
The “Drilling” is where they get the pipe under the stream – no idea how long this will take so guessed at 2 weeks.

THIS IS JUST MY GUESS THOUGH ! it’s not the actual Wessex Water plan.
I thought it was the least I could do after all the work put in by Inspector Moulder !